Project 05 — Modernize Computer Equipment Rooms
Location: City Data Center / South Corp Yard
This project replaces critical battery backup power and large-scale cooling units that support Scottsdale’s primary data centers. These systems ensure that city eServices and emergency communications remain online during extreme weather or power outages.
Total Investment: $2,117,700
| Project Title | Funding Source | Total Cost | Spent to Date | Remaining Budget |
| Modernize Computer Equipment Rooms | General Fund | $1,426,100 | $90,800 | $1,335,300 |
| 2019 GO Bond – Q3 | $691,600 | $273,600 | $418,000 |
Source: City of Scottsdale Tentative CIP Packet 2025/2026 Fiscal Year